A giant module for Novatek’s Arctic LNG 2 project sails the Northern Sea Route

The production facility, which will be part of the project's first train, heads to Belokamenka before being towed to the Gydan peninsula for final installation.

By Atle Staalesen, The Independent Barents Observer September 7, 2021
1709
The GPO Grace departed the Wison Offshore and Marine yard in China on August 19 and is now sailing towards Murmansk via the Northern Sea Route. (GPO Heavylift via The Independent Barents Observer)

A giant module built for the first train in Novatek’s Arctic LNG 2 plant is sailing north.

The module was built at Wison Offshore and Marine’s Zhoushan yard in China and is now being shipped towards Novatek’s Kola yard in Belokamenka north of Murmansk where it will be mounted to a large gravity-based structure before being towed to the coast of far northern Gydan Peninsula in Ob Bay in Siberia.

Production at Arctic LNG 2’s first train is scheduled for 2023. A year later, in 2024, Train 2 will start production, while the final Train 3 is set to start operation in 2025.

Each of the three trains will have a production capacity of 6.6 million tons of liquefied natural gas per year, according to Novatek.

The company is Russia’s largest privately-owned natural gas company and is today operating the Yamal LNG plant in Sabetta. Unlike Yamal LNG, the Arctic LNG 2 will entirely be based on a floating production concept.

The Norwegian GPO Heavylift’s vessel GPO Grace is bringing the LNG production plant from China to Murmansk. It’s one of the largest structures ever transported via the Arctic shipping lane. On September 2, the vessel sailed northbound outside the Kamchatka Peninsula, according to AIS data. Estimated arrival at the Kola yard in Belokamenka is September 16.

Construction on a giant barge designed to hold Train 1 for Arctic LNG 2 takes place at Kola Yard in Belokamenka north of Murmansk. (Novatek via The Independent Barents Observer)

The GPO Grace, though, isn’t the only giant open-deck transport vessel to sail the Northern Sea Route this September. Currently, the Biglift Barentsz sails west in the East Siberian Sea with an estimated arrival to Gydan in the Ob bay on September 10. The ship brings infrastructure facilities to the ongoing preparation for Arctic LNG 2. Construction of pipelines, pump stations, housing, an airport, and port facilities are in full swing. According to online ship-tracking service MarineTraffic.com, there are currently more than 40 vessels near the location on the eastern shores of the Ob Bay.

August, September, and October are the busiest months for shipping of construction materials to the area, as the Ob Bay and waters in the Kara Sea are mostly ice-free.

The Arctic LNG 2 will process gas from Utrenneye field on the Gydan Peninsula in the Yamalo-Nenets Autonomous Okrug.

When the investment decision for the project was made in September 2019, the total costs for bringing the Arctic LNG 2 to full capacity were estimated at $21.3 billion.

Novatek holds a 60 percent share in the project, while TotalEnergies, China National Petroleum Corporation and China National Offshore Oil Corporation hold 10 percent each. That last 10 percent belongs to a consortium of the two Japanese corporations JOGMEC and Mitsui.

Like the LNG produced at the Sabetta plant, the Arctic LNG 2 will ship the gas to markets both in Asia and Europe. A large fleet of ice-classed LNG tankers will sail east and west, and two reloading facilities are to be established, in Ura Guba on the Kola Peninsula for European shipping and another at Kamchatka for the Asian market.