Delivery of final modules for Russia’s Arctic LNG 2 project highlights challenge of designing effective sanctions
Based on satellite images, multiple industry sources, including those familiar with engineering work at Belokamenka, and Novatek project documents, Red Box’s vessels carried modules TMS-003 and TMS-004, part of the plant’s refrigeration process that turns gas into its liquefied counterpart.
Audax and Pugnax arrived at Belokamenka last week and transferred the modules to the Material Offloading Facility or MOF. Here they will be integrated onto a floating production platform the size of eight soccer pitches.
In a sense Adkins is not wrong when he says that Red Box is simply delivering “steel structures.”
However, the structures are carefully engineered to house hundreds of millions of USD of equipment to compress and produce LNG. Each module can weigh up to 14,000 tons.
When does it become more than a “steel structure?”
The two modules delivered to Belokamenka last week are designed to accommodate gas turbines driving compressors and house refrigeration string A and B, Novatek documents show. The refrigeration process was subsequently re-designed to replace gas turbines with electric drives when American supplier Baker Hughes did not deliver the required gas turbines.
As such the modules should fall under the EU’s 5th round of sanctions from May 2022 prohibiting “the sale, supply, transfer or export, directly or indirectly, goods or technology suited for the liquefaction of natural gas.”
However, the specific technology used to produce the LNG, e.g. motors and compressors, may have been shipped separately to Belokamenka to be added to the modules on site.
Initial photographs of the modules at Belokamenka did not offer a definitive answer.
“I could not identify if the electric motors and compressors were installed though. The installation will likely happen in Belokamenka. So technically yes, those are only steel structures,” explains Mehdy Touil, a LNG Operations Specialist, who in the past worked as a senior operator for Novatek’s neighboring Yamal project.
At what point does a “steel structure” become more than just an assemblage of I-beams and pipes? And at what point does a module that is clearly designed to house equipment to liquefy natural gas become sanctioned technology for the production of LNG?
If you ask Red Box’s Adkins, even a 14,000 ton module that took hundreds of shipyard workers and engineers 18 months to assemble is still just a “steel structure,” independent of what its final purpose may be.
“The argument that they may not know what the modules are for is nonsense, these steel structures delivered to Arctic ports do not have any other use but to be part of the gas liquefaction plants,” explains researcher Frédéric Lasserre, director of the Conseil québécois d’études géopolitiques (Quebec Council for Geopolitical Studies).
Referencing an earlier investigation by Le Monde Lasserre worked on, he says, “it was apparent that Red Box tried to conceal they were very involved in any wrongdoing.”
Bureaucracy can be your friend
According to Red Box, the modules are designated as “steel structures” using export Harmonized System (HS) Codes, a standardized 10-digit code to classify products for export by the International Trade Administration (ITA), a US government agency; seemingly turning them into benign towers of Chinese steel 40 meters tall immune to Western sanctions.
“They pretend they ignore the use of the delivered goods, quite likely indeed basing their position on the goods identification system. With good lawyers or customs brokers, there are likely faults in the system that they exploit,” concludes Lasserre.
Similar to Red Box, France’s Technip argued that some of the modules of the LNG plant could be sent to Russia without contravening sanctions “because they are not directly involved in the processing of LNG.”
It is also not uncommon for custom codes to differ between export and import, a procedure that has been used to circumvent sanctions.
An investigation by the Investigative Reporting Project Italy (IRPI) details how HS codes and the extremely complex international import and export rules have been used by Arctic LNG-affiliated companies to reclassify equipment from one category to another.
Red Box has faced no lack of scrutiny with multiple reports by HNN, Le Monde, the Financial Times, and others over the past year.
The fact that Red Box continues to escape secondary sanctions by the US – which just last week announced new measures against 500 companies and persons including several affiliated with Arctic LNG 2 – suggests Adkin’s statements that his company is not violating sanctions hold water; or that it has at least found the right legal channels to navigate the icy seas of international sanctions.
High North News is an independent newspaper published by the High North Center at Nord University in Bodø, Norway.