Russia’s nuclear icebreaker program runs into delays

By Atle Staalesen, The Independent Barents Observer March 2, 2017
1316
Atomic icebreaker Arktika under construction is seen at the Baltic Shipyard in St. Petersburg, Russia October 26, 2016. Picture taken October 26, 2016. (Interpress / Yevgeny Stepanov / via Reuters)
Atomic icebreaker Arktika under construction is seen at the Baltic Shipyard in St. Petersburg, Russia October 26, 2016. Picture taken October 26, 2016. (Interpress / Yevgeny Stepanov / via Reuters)

The construction of Russia’s first LK-60 nuclear icebreaker, the Arktika, might be at least a year delayed following troubles at the Baltic Yard in St. Petersburg. According to the newspaper DP, the yard has addressed the Russian government with a request to postpone the launch of the powerful vessel to December 2018.

Originally, the Arktika was to be ready for sailing in December 2017.

[Russia looks to add new nuclear icebreaking capacity]

The yard blames its subcontractors for the delays. Among them is the Kirovsky Zavod, which is manufacturing the ships’ steam turbines. Baltic Yards and its superiors in the United Shipbuilding Corporation now instead wants to hand over the contract to the Kaluga Turbine Plant and has launched a court case against the Kirovsky Zavod.

The yard has reportedly also sued the Krylov State Research Center for failing to deliver design for the turbines in time.

A key reason for the trouble is the difficult relations between Russia and western nations. The steam turbines were originally to be delivered by Turboatom, the Ukrainian company based in Kharkiv. However, the ongoing conflict with Ukraine put a stop to that deal.

A key role was originally also given to a British company owned by General Electric. The company was to deliver electric propulsion systems for the ships. However, also that deal was stalled, reportedly because of the freeze in east-west relations.

[Northern Sea Route icebreaker escorts are up by 100 percent]

The Baltic Yard is building three LK-60 icebreakers. The first of the ships, the Arktika was put on the water in June 2016. Construction of the two other vessels, the Ural and the Sibir, was launched in May 2015 and July 2016.

The yard’s construction contract with Rosatom, the state nuclear power company, amounts to 123 billion rubles, DP reports.

The ships LK-60 (project 22220) will be the most powerful icebreakers in the world. They are equipped with the RITM-200 nuclear propulsion unit with two 175 MW capacity reactors and are able to break through three meter thick ice. The ships will be 173 meters long and 34 meters wide. They will be based in Murmansk as part of the state-owned Rosatomflot fleet of nuclear icebreakers.